TFS Aggregator Common Use Cases

July 7, 2018

After receiving several questions about my previous post about Meeting the TFS Aggregator I decided to go deeper in this topic with a new post.
The idea is to expose some common use cases and their implementation for them that are getting started.
Before reading the post I highly recommend reading the official documentation to understand the syntax basics.

 

Let’s implement the following use cases:

  • Update PBI state to “Committed” when any child gets moved to “In Progress”
  • Update PBI state to “Done” when all childrens get moved to “Done” or “Removed”
  • Set a “calculated” field in a Task
  • Create new work items and links
  • Update a PBI field according to the value of the children
  • Update children field values according to the parent changes (when the parent changes)
  • Aggregate the field “Remaining Work” in a PBI with the children “Remaining Work” values

 

Update PBI state to “Committed” when any child gets moved to “In Progress”
When any task is moved to “In Progress” move it’s parent to “Committed”.

<rule name="AutoCommittedByChildren" appliesTo="Task" >
	<![CDATA[
		if (new[] {"In Progress"}.Contains((string)self["System.State"]))
		{
			if(self.HasParent() && ((string)self.Parent["System.State"]) != "Committed")
			{
				self.Parent.TransitionToState("Committed", "Updated Automatically By TFS Aggregator");
			}
		}      
	]]>
</rule>	

 

Update PBI state to “Done” when all childrens get moved to “Done” or “Removed”

<rule name="AutoDoneByChildren" appliesTo="Task">
    <![CDATA[
		if ((string)self["System.State"] == "Done" && self.HasParent() && ((string)self.Parent["System.State"]) != "Done")
		{
			if (self.Parent.Children.All(child => new[] {"Removed", "Done"}.Contains((string)child["System.State"])))
			{
				self.Parent.TransitionToState("Done", "Updated Automatically By TFS Aggregator");
			}
		}
    ]]>
</rule>	

 

Set a “calculated” field in a Task

Set the field “Estimated Work” with the sum of “Estimated Dev Work” and “Estimated Test Work”.

<rule name="CalculatedEstimatedWorkField" appliesTo="Task" >
	<![CDATA[
		self["Custom.EstimatedWork"] = (double)self["Custom.EstimatedDevWork"] + (double)self["Custom.EstimatedTestWork"];
	]]>
</rule>

 

Create new work items and links
When a PBI is opened, create a linked task with the same title, iteration path and area path as child.

<rule name="CreateAutomaticTasksForPBI" appliesTo="Product Backlog Item" >
	<![CDATA[
		if ((string)self["System.State"] == "New" && ((int)self["System.Rev"]) == 1) 
		{
			if(!self.HasChildren()) 
			{
				var child = store.MakeNewWorkItem((string)self["System.TeamProject"], "Task");
				child["Title"] = self["Title"];
				child["System.IterationPath"] = self["System.IterationPath"];
				child["System.AreaPath"] = self["System.AreaPath"];
				child.AddWorkItemLink(self, WorkItemImplementationBase.ParentRelationship);
			}
		}
	]]>
</rule>

 

Update a PBI field according to the value of the children
Set the field “Estimated Work” in the PBI with it children “Estimated Work” sum.

<rule name="CalculateByChlidrenEstimatedWork" appliesTo="Task">
	<![CDATA[
		if (self.HasParent())
		{
			var parent = self.Parent;
			parent["Custom.EstimatedWork"] = parent.Children.Sum(task => task.GetField<double>("Custom.EstimatedWork", 0d));
		}
	]]>
</rule>

 

Update children field values according to the parent values (when the parent changes)
Set “Iteration Path” and “Area Path” fields according to the parent values when the Area/Iteration path is updated in the PBI.

<rule name="UpdateAreaAndIterationByParentChanges" appliesTo="Product Backlog Item" >
	<![CDATA[
		if(self.HasChildren()) 
		{
			foreach (var child in self.Children) 
			{
				if (((string)self["System.IterationPath"]) != ((string)self.LastRevision.Fields["System.IterationPath"].OriginalValue))
				{
					child["System.IterationPath"] = self["System.IterationPath"];
				}				
				if (((string)self["System.AreaPath"]) != ((string)self.LastRevision.Fields["System.AreaPath"].OriginalValue))
				{
					child["System.AreaPath"] = self["System.AreaPath"];
				}
			}					
		}      
	]]>
</rule>	

 

Aggregate the field “Remaining Work” in a PBI with the children “Remaining Work” values
When Task is updated aggregate the parent “Remaining Work” value (upate the total remaining work by calculating [total – delta]).
For this rule we will create a hidden field called “PreviousRemainingWork” in the Task to calculate the delta.

<rule name="AggregateParentRemainingWork" appliesTo="Task" >
	<![CDATA[
		double delta = (double)(self["Custom.PreviousRemainingWork"]??0d) - (double)(self["Microsoft.VSTS.Scheduling.RemainingWork"]??0d);
		self.Parent["Microsoft.VSTS.Scheduling.RemainingWork"] = (double)(self.Parent["Microsoft.VSTS.Scheduling.RemainingWork"]??0d) + delta;
		self["Custom.PreviousRemainingWork"] = (double)(self["Microsoft.VSTS.Scheduling.RemainingWork"]??0d);
	]]>
</rule>	

 

Putting All Together
Create a policies file (TFSAggregator.ServerPlugin.policies) with the content below:

<?xml version="1.0" encoding="utf-8"?>

<AggregatorConfiguration>
    

	<!-- Configuration -->
    <runtime debug="false">
        <rateLimiting interval="00:00:01.00" changes="1" />
        <logging level="Normal" />
        <script language="C#" />
        <authentication autoImpersonate="false" />
    </runtime>
   


	<!--Rules-FirstPolicy-->	
    <rule name="AutoCommittedByChildren" appliesTo="Task" >
		<![CDATA[
			if (new[] {"In Progress"}.Contains((string)self["System.State"]))
			{
				if(self.HasParent() && ((string)self.Parent["System.State"]) != "Committed")
				{
					self.Parent.TransitionToState("Committed", "Updated Automatically By TFS Aggregator");
				}
			}      
		]]>
	</rule>	

	<rule name="AutoDoneByChildren" appliesTo="Task">
		<![CDATA[
			if ((string)self["System.State"] == "Done" && self.HasParent() && ((string)self.Parent["System.State"]) != "Done")
			{
				if (self.Parent.Children.All(child => new[] {"Removed", "Done"}.Contains((string)child["System.State"])))
				{
					self.Parent.TransitionToState("Done", "Updated Automatically By TFS Aggregator");
				}
			}
		]]>
	</rule>

	<rule name="CalculatedEstimatedWorkField" appliesTo="Task" >
		<![CDATA[
			self["Custom.EstimatedWork"] = (double)self["Custom.EstimatedDevWork"] + (double)self["Custom.EstimatedTestWork"];
		]]>
	</rule>
	


	<!--Rules-SecondPolicy-->	
	<rule name="CreateAutomaticTasksForPBI" appliesTo="Product Backlog Item" >
		<![CDATA[
			if ((string)self["System.State"] == "New" && ((int)self["System.Rev"]) == 1) 
			{
				if(!self.HasChildren()) 
				{
					var child = store.MakeNewWorkItem((string)self["System.TeamProject"], "Task");
					child["Title"] = self["Title"];
					child["System.IterationPath"] = self["System.IterationPath"];
					child["System.AreaPath"] = self["System.AreaPath"];
					child.AddWorkItemLink(self, WorkItemImplementationBase.ParentRelationship);
				}
			}
		]]>
	</rule>

	<rule name="CalculateByChlidrenEstimatedWork" appliesTo="Task">
		<![CDATA[
			if (self.HasParent())
			{
				var parent = self.Parent;
				parent["Custom.EstimatedWork"] = parent.Children.Sum(task => task.GetField<double>("Custom.EstimatedWork", 0d));
			}
		]]>
	</rule>

	<rule name="UpdateAreaAndIterationByParentChanges" appliesTo="Product Backlog Item" >
		<![CDATA[
			if(self.HasChildren()) 
			{
				foreach (var child in self.Children) 
				{
					if (((string)self["System.IterationPath"]) != ((string)self.LastRevision.Fields["System.IterationPath"].OriginalValue))
					{
						child["System.IterationPath"] = self["System.IterationPath"];
					}				
					if (((string)self["System.AreaPath"]) != ((string)self.LastRevision.Fields["System.AreaPath"].OriginalValue))
					{
						child["System.AreaPath"] = self["System.AreaPath"];
					}
				}					
			}      
		]]>
	</rule>	

	<rule name="AggregateParentRemainingWork" appliesTo="Task" >
		<![CDATA[
			double delta = (double)(self["Custom.PreviousRemainingWork"]??0d) - (double)(self["Microsoft.VSTS.Scheduling.RemainingWork"]??0d);
			self.Parent["Microsoft.VSTS.Scheduling.RemainingWork"] = (double)(self.Parent["Microsoft.VSTS.Scheduling.RemainingWork"]??0d) + delta;
			self["Custom.PreviousRemainingWork"] = (double)(self["Microsoft.VSTS.Scheduling.RemainingWork"]??0d);
		]]>
	</rule>	
	


	<!-- Policies -->
    <policy name="FirstPolicyName">
	
        <collectionScope collections="TfsCollectionName" />
        <projectScope projects="TfsTeamProjectName" />
        
        <ruleRef name="AutoCommittedByChildren" />
		<ruleRef name="AutoDoneByChildren" />
		<ruleRef name="CalculatedEstimatedWorkField" />
        
    </policy>	

	<policy name="SecondPolicyName">

        <collectionScope collections="TfsCollectionName" />
        <projectScope projects="TfsTeamProjectName" />
        
        <ruleRef name="CreateAutomaticTasksForPBI" />
		<ruleRef name="CalculateByChlidrenEstimatedWork" />
		<ruleRef name="UpdateAreaAndIterationByParentChanges" />
		<ruleRef name="AggregateParentRemainingWork" />
        
    </policy>
    
</AggregatorConfiguration>

 

Some Tips

  • Remember that fields can be null (avoid exceptions)
  • Use the logger to trace your steps
  • Avoid infinite loops (use the rateLimiting configuration)
  • Use hidden fields for calculated rules that require aggregation
  • Use reference names attribute instead of the field name
  • Source control your changes (using Git, TFVC, etc)

 
 