What Is A Good Time Frame For A Task?

יום שלישי, אפריל 7, 2009

The answer is 2 – 5 days! I am working with a lot of project managers and team leaders and when they show me there project plans I see tasks that are half a day, a day and many times I see tasks that are more than a week. I like to clarify a few points before I continue: When talking about tasks I talk about any type of task, for example tasks for testers, programmers, IT etc. There are tasks that are estimated to more than 5 days, these are high level tasks that will be divided later to smaller tasks. It...