This post is the second post out of Five that builds the TFS 2010 Work Items Basic Guide. See the first post: “TFS 2010 Work Items Basic User Guide – Introduction”


On this post I will show different ways to create new work items from the Team Explorer 2010.


In order to show the Team Explorer in Visual Studio click on its icon.


Pic_1_Icon


There are two main methods to create Work Items, from the Team Explorer –> Work Items menu or from the Team tab.


In order to create a new work item from the Team Explorer –> Work Items menu do the following:


Right click the Work Items menu item choose the "Add Work Item" and choose the Work Item type you like to create from the list of Work Item types.


Pic_2_Open_Bug


Pic_3_Open_Bug_Second_Time


In order to create a new work item from the Team tab do the following:


Click the Team tab choose the "Add Work Item" and choose the Work Item type you like to create from the list of Work Item types.


Pic_3_Open_Bug


The result of both methods is the same, a new form of the chosen Work Item type.


Next guide part: "TFS 2010 Work Items Basic User Guide – Work Item Link Types"


Have Fun!!!

הוסף תגובה
facebook linkedin twitter email

כתיבת תגובה

האימייל לא יוצג באתר. שדות החובה מסומנים *

2 תגובות

  1. Karenיוני 23, 2010 ב 11:45

    This is not TFS2010 work items menu I see now. I see "product backlog item", "sprint", sprint backlog item, etc.. could you update the guide?

    הגב
  2. Eran Rusoיולי 1, 2010 ב 8:39

    Hi Karen,

    What you see comes from a different template then the one I have used.

    The work item types are configurable, so you can create what ever types you like.

    I can guess that the template you use is the SCRUM template by the work item types names.

    Have Fun!!!